CaseLock Community Investigation

Petersburg, Virginia
Data Center Pipeline Investigation

Petersburg, Virginia · July 26, 2026

Four data-center projects totaling roughly 397 acres are advancing through Petersburg's industrial districts. In 2024 the City amended its zoning code (Ordinance 24-ZTA-07) to allow data centers by-right in M-1/M-2 industrial districts — meaning no public hearing is required before construction.

4 Data CentersBy-Right ZoningWater Risk
Read the Petersburg Investigation (PDF)

The Four Projects

ProjectStatus / Notes
NuVu Real EstateData center — M-1 industrial, by-right under Ordinance 24-ZTA-07
Menlo DigitalData center — M-1/M-2 industrial district
Wagner Properties / GFYAData center — by-right, no public hearing required
Warrenton Group / TWGData center — by-right, no public hearing required

Combined footprint: ~397 acres. All four sit in industrial districts rezoned by-right in 2024, so none triggered a public hearing.

By-Right Zoning (Ordinance 24-ZTA-07)

No Public Hearing Required

In 2024 Petersburg amended its zoning ordinance to permit data centers by-right in M-1 and M-2 industrial districts. The practical effect: a developer can build without a discretionary review, a conditional-use permit, or a public hearing — removing the main forum residents had to object.

Water — ARWA / Lake Chesdin

Appomattox River Water Authority
Water Authority
Appomattox River Water Authority (ARWA) — Lake Chesdin
Permitted Capacity
96 MGD
Current Output
~33 MGD
Pool Level
1.5 inches below full
Google Permit Request
30 MGD
Risk
Four new data-center loads layered on top of a 30 MGD Google draw
The system is already drawing only ~33 MGD against a 96 MGD permit with the pool 1.5 inches low — and Google alone has requested a 30 MGD allocation. Layering four new data-center loads on top raises the risk of a supply shortfall during drought.

City Officials

Mayor Parham
Mayor, City of Petersburg
Arnold Westbrook Jr.
City official named in the investigation
Jeff Stoke
City official named in the investigation
Jared Crews
City official named in the investigation

Named in the July 26, 2026 investigation. Contact the Petersburg City Clerk's office to request meeting minutes and public records.

Community Opposition

Ramblewood Neighborhood

Residents nearest the pipeline organizing against the by-right approvals.

Nathan Howard

Community organizer raising water-supply and zoning concerns.

Scott Perkins

Resident advocate tracking the four-project pipeline.

Petersburg on the Map

For development purposes only
For development purposes only
For development purposes only
For development purposes only
For development purposes only
For development purposes only
For development purposes only
For development purposes only
For development purposes only
For development purposes only
For development purposes only
For development purposes only
3
Google
Map data ©2026
Map data ©2026
This page can't load Google Maps correctly.
Do you own this website?
Transmission Lines
5 pins · 0 lines
Active / threatPending / monitoringInvestigation / defaultPin TypesSurveillance CameraWater ContaminationCommunity VictoryOfficial ConflictUtility / PowerUnder InvestigationMeeting / CoordinationLaw Firm / AttorneyCivil War BattlefieldArchaeological SiteCemetery / Burial GroundCorporate EntityInfrastructureActive transmission lineProposed / inactive line
Download the Petersburg Investigation (PDF)

Compiled by CaseLock from Petersburg City public records, zoning ordinance 24-ZTA-07, and ARWA water data.
This is an informational community investigation, not legal advice. Residents with direct concerns should consult an attorney.